Construction Photos
Exciting progress is being made at the campsite! With each day, camp begins to look more and more like the magical place it will be upon opening next summer. Construction photos and an update from our Facilities Manager Paul St. Ruth are posted monthly – be sure to check back and view our progress. The Archived Construction Photos section shows how far we have come in building the camp.
March 2010
Medical and Administration Building

The architect's rendition of the Medical and Administration Building along with the inspiration for the design, a train depot.
Construction on the building commenced in January 2010, and as illustrated below, the building is beginning to resemble the finished structure. Excavation, foundation, groundwork, and slab work on the Medical and Administration Building are complete, and roofing has begun.

The Medical and Administration Building (30 March 2010)

The Medical and Administration Building, March 30, 2010

An view of the interior of the Medical and Administration Building

A view of camp through the door in the Medical and Administration Building. This will be the site campers see as they enter camp.
Dining Hall

The architect's rendition of the completed dining hall, modeled after an Old Red Barn
Construction of the Dining Hall commenced on March 22, 2010 and excavation and foundation work is underway. The backfill, ground work and slab work will continue through the month of March, and framing will begin in early April.

The foundation of the dining hall (30 March 2010)
General Site Update
- The project is on schedule for partial occupancy in January 2011 and will open for first camp session in June 2011
- Our sanitary sewer main construction is complete. Storm sewer and water main construction are under way.
Future Construction Plans
- We will begin construction on”The Barn”, our Maintenance/Storage Building, in the beginning of April
- Construction on The Lodge will begin mid-April
- The camper cabins will be constructed in a staggered patter every two weeks between July and September. We will construct 6 cabins during this period.